Andritz Slovakia Production Capacity Expansion.

Completed.

Humenné

In the city of Humenné, we carried out the construction of the project “Expansion of Production Capacities for Andritz Slovakia,” which, with its production facilities in Humenné and Spišská Nová Ves, is part of the international Andritz AG Group, headquartered in Graz, Austria. The project involved the construction of a new production hall located on a site within the Gutmanovo industrial park. The hall will be used for the production of knives for the steel industry and other sectors.

| 22. 07. 2024

ANDRITZ HUMENNÉ EXPANSION PROJECT NEARING COMPLETION – FINAL WORKS IN PROGRESS!

THE CONSTRUCTION OF THE FACILITY IS PROGRESSING SUCCESSFULLY!

At Andritz in Humenné, we have completed the green roof and are preparing the terrain for the construction of paved areas. Inside the hall, the installation of technologies required for production is underway, while work on the interiors of the administrative part of the building is also continuing.

| 05. 06. 2024

| 05. 04. 2024

PRODUCTION HALL HANDOVER – PHASE 1 COMPLETED.

Fire protection penetrations, as well as gas, electricity, and water installations, are being carried out. Inside the hall, we have concreted the floor with a rail track. On the administrative building, the construction of the roof structure is in progress, and we are starting with the adjustment of the paved areas.

THE PRODUCTION HALL FRAME IS ENCLOSED.

We have completed the covering of the roof structure with a membrane roofing system, and the sheet metal components of the façade have also been finalized. Work continues in the interior, where HVAC installations, electrical works, floor thermal insulation, and waterproofing of the building are in progress. Additionally, the concreting of the foundation slab of the administrative building has begun.

| 09. 02. 2024

| 24. 01. 2024

Take a look behind the scenes of the construction process.

In Humenné, the installation of the roof structure, implementation of plumbing systems, and assembly of steel structures are currently underway in the main hall of the facility. In the administrative building, we are carrying out the installation of horizontal sewerage and reinforcement binding for the topping of Spiroll ceiling slabs.

REINFORCED CONCRETE FRAME.

We have reached another significant milestone in the construction – the reinforced concrete structure is now being implemented! The main building will consist of a standalone single-story production hall with a three-story administrative section, designed as an independent structural unit.

| 08. 01. 2024

| 03. 11. 2023

EARTHWORKS AND PILING.

We are carrying out earthworks and working on the foundation of the building with reinforced concrete footings and large-diameter piles. From there, the structure will begin to rise upwards.

Site handover completed – construction begins.

| 26. 09. 2023