New Construction of a Kindergarten

Completed

Hrčeľ

In the village of Hrčeľ, a new kindergarten has been completed, providing a modern, safe, and stimulating environment for the youngest children

THE FINALE IS HERE.

The main construction work has been completed, and the final finishing touches and detail adjustments are currently underway. Starting in September, the newly built facility will be ready to welcome its first young students in modern and safe spaces that meet all current preschool education standards. We are pleased to have been part of this important project for the community and believe that the kindergarten will serve both children and educators for many years to come.

| 19. 06. 2025

| 28.05.2025

WE ARE APPROACHING THE FINAL STAGE.

We are currently finalizing the building’s facade, giving it its finished appearance. Solar panels have been installed on the roof to ensure eco-friendly and cost-efficient operation of the facility. Outside, we have completed the construction of exterior staircases, and the access road and parking lot have been asphalted, improving comfort and safety for children, parents, and staff. Inside, flooring is being laid, walls are being tiled, and interior doors are being installed. Very soon, we will hand over modern and fully functional spaces ready for education and learning.

STEP BY STEP.

Construction is successfully progressing according to plan. We are currently completing the full insulation of the building and beginning to install the facade. At the same time, windows are being fitted, and inside the building, we continue assembling drywall partitions, gradually creating new spaces for children and staff. We are also working intensively on the installation of electrical, water, and heating systems. Roofing work has been completed, allowing us to fully focus on the next phases of construction.

| 24. 04. 2025

| 21.03.2025

WE ARE MAKING PROGRESS.

The kindergarten is literally taking shape before our eyes! After completing the steel framework, we are moving forward with enclosing the building, including insulation, installation of the roof sheets, and assembly of drywall partitions. Construction is progressing according to plan, and window and door installation will begin soon. We’re excited that each day brings us one step closer to creating a modern and cozy environment for our little ones!

FRAMEWORK.

In the past two weeks, our team has accomplished a lot! After completing the foundation walls, we moved on to assembling the steel framework, and the kindergarten is now beginning to take its first real shape.

| 13. 02. 2025

| 28. 01. 2024

FOUNDATIONS.

Construction at the kindergarten is progressing! Our team is building the foundation walls and insulating them. Excavation for the detention tank and underground sewage is underway. In the coming days, we plan to start assembling the steel frame.

WE ARE STARTING.

Our team has begun construction! After taking over and fencing the site, we are carrying out the first excavation works, bringing the village of Hrčeľ one step closer to its new kindergarten.

| 27. 11. 2024

In the village of Hrčeľ, a new kindergarten has been completed, providing a modern, safe, and stimulating environment for the youngest children.